Queensbridge, Hackney — complete
Combustible façades stripped back to the existing SFS and replaced with A2-s1,d0 systems while residents remained in occupation. We designed our package at RIBA Stages 4 and 5 in accordance with tested systems and installed three non-combustible systems, with cavity barriers at floors, party walls, openings and system changes.
Close-out: EWS1, FRAEW and Building Control sign-off are complete. A PAS 9980 FRAEW was completed for the remediated façades and the works were signed off under the Building Regulations. All replacement cladding specified and installed to A2-s1,d0 as a minimum.